Solar and re-roofing

Should you fit solar panels when you replace the roof?

The short answer

The two jobs are best decided together, because panels sit on the covering and a roof that needs replacing is a roof the panels will have to come off. On a house, roof solar can be permitted development under Part 14 Class A within set limits, and the Planning Portal says the roof's ability to carry the panels will need to be checked. Plan the covering and the panels as one sequence.

Panels sit on the covering, so the two jobs share one roof. How the rules treat roof solar and why the order of the work matters.

New EPDM membrane and drip trim on a garage roof edge

Planning: Part 14, not Class C

A house re-roof is a Class C matter under the General Permitted Development Order, and Class C leaves solar out. It excludes any alteration that would include the installation, alteration or replacement of solar photovoltaics or solar thermal equipment. Panels are therefore a Part 14 Class A matter, with their own limits:

Part 14 Class A limits for roof solar on a house
RoofNot permitted if
PitchedIt protrudes more than 0.2 metres beyond the roof slope, or stands higher than the highest part of the roof, excluding any chimney
FlatIt is more than 0.6 metres higher than the highest part of the roof, excluding any chimney
Listed houseThe dwellinghouse is a listed building

The panels must also be sited, as far as practicable, to minimise their effect on the external appearance of the building. Part 14 also bars them "on a site designated as a scheduled monument". The measure is how far the equipment protrudes beyond the slope, so the mounting system and its depth belong in the calculation, not just the panel itself.

Conservation areas and Article 4

Protected land adds a step. On a flat roof on article 2(3) land, which takes in conservation areas, a National Park and a National Landscape, the developer must apply to the local planning authority for a determination before beginning. An Article 4 direction can withdraw the right altogether: Langstone's direction for Havant lists the installation of solar equipment among the alterations it controls.

Nothing is assumed from the postcode. The council for your address says whether the house sits on protected land, and what any direction covers. Where there is doubt, the safe step is to ask before the panels or the covering are ordered. For planning queries at a Havant address, Havant Borough Council's customer services line is 023 9244 6019.

A listed house is outside Part 14 permitted development, so panels there are a question for the council, and listed building consent comes into it as well. Our planning guide sets out how listed homes are treated, and the answer on solar panels on a flat roof covers that kind of roof.

The load, the covering and Building Regulations

The Planning Portal's solar page puts it in two lines: "If you wish to install a solar panel on your roof building regulations will normally apply." and "The ability of the existing roof to carry the load (weight) of the panel will need to be checked and proven."

That check is a second weight question on a roof that may already be getting a new covering. A new covering that is 15 per cent or more heavier raises an approval question of its own, so the survey for a re-roof and the check for the panels draw on the same facts about what the timbers can carry. Our answer on changing to heavier roof tiles sets out that test.

Energy Saving Trust guidance wants the covering left undisturbed by the panel fixings. Every fixing is a point where the covering has been opened up and has to be made good, so ask who does that and who answers for it afterwards.

If the same job renovates more than half of the roof, Part L's insulation test applies as well, and our answer on insulation when re-roofing sets out its figures. Settling that before the covering goes on is simpler than reopening the roof for panels later.

Getting the order of the work right

A solar installer fits the panels, and the roof has to be ready for them. The order that makes sense follows from the roof:

  1. Survey the roof and decide whether it is mended or replaced.
  2. If it is to be replaced, lay the new covering and finish the roof.
  3. Check the roof's load and the planning position, and fit the panels afterwards.

The reason is simple. A covering with little life left means the panels have to come off to renew it, and the saving from fitting panels is not worth a roof that has to be stripped soon after. HomeBuilding's approximate lifespans, 60 to 80 years for clay tiles and 40 to 50 years for plain concrete tiles, help to judge what is left in a roof that is not being replaced.

Ask for the survey notes and photographs to go to the installer, with the covering named in the written quote. Panels that need cleaning later carry a cost too: MyJobQuote (October 2026) gives an average of around £150 to clean solar panels. For the wider job, see new roofs.

Related questions

Does a conservation area change the rules for roof solar?

It can. On a flat roof on article 2(3) land the developer must apply to the local planning authority for a determination before beginning, and an Article 4 direction can remove the right altogether. Ask the council for your address what applies, since boundaries and directions differ from one place to the next.

Does the roofer need to be told about solar plans before the quote?

Yes, because the survey looks at the roof's load and at the covering that will carry the panels. The written quote is one total after the survey and can name the covering, so the installer starts from a record of the roof and its condition. Photographs of the finished roof go with it.