The short answer

No, not if the new covering is 15 per cent or more heavier. The Planning Portal says that needs Building Regulations approval, and it tells you to get a structural engineer or surveyor to look at the roof first. Approved Document A counts an increase of more than 15% in the loading upon the roof as a significant change. A change of tile also moves the pitch and fixing questions, so the survey looks at them together.

A heavier covering raises a question about the roof's loading before it raises one about looks. Where the 15 per cent line sits.

A ladder against a brick bungalow with a tiled roof

Where the 15 per cent line comes from

Two official texts draw the line, and each uses its own wording. The Planning Portal's re-roofing guide lists the cases where approval is needed:

  • A new covering material whose weight lies 15 per cent or more above that of the old roof covering.
  • A new covering that would behave in a fire in a significantly different way from the old one.

Approved Document A, in its 2004 edition incorporating the 2004, 2010 and 2013 amendments, says a significant change in roof loading is when the loading upon the roof is increased by more than 15%. The Portal's "or more" and the Approved Document's "more than" part company only at exactly 15 per cent, which is not a figure a survey ever aims for. The safe reading is to treat the line as a limit, and to put any change that comes near it to building control.

Neither text names a tile or a slate. The weight difference between two coverings depends on the exact products chosen, so the comparison is made on the manufacturers' data sheets, never on the names of the materials. The covering you are leaving and the one you want both go on that comparison.

What a structural check is for

The Portal recommends that a structural engineer or surveyor sees the roof before work commences. The purpose is to learn whether the roof structure under the covering can carry the new load. A roof that has stood for decades under one covering has not shown that it can carry another.

The check also answers a question that a quote cannot settle alone: whether anything in the structure needs strengthening before the new covering goes on. That is a finding for the engineer or surveyor to make once they have seen the timbers, and a view from the ground cannot stand in for it.

Approval itself is a separate step. Building control is carried out by the council's building control team or by a registered building control approver. At a Havant address, the Building Regulations route is agreed with your building control body ahead of the first day on site, and with a heavier covering that conversation comes first. The answer is then in hand when the written quote is drawn up, and the price does not move halfway through the job because a check was left until the scaffold was up.

What else changes when the tile changes

Weight is only one thing that follows a different product. Each tile and slate has its own minimum pitch, and Marley's published figures show how far apart they sit.

Minimum pitch for four Marley concrete tiles
TileMinimum pitch
Mendip 12.512.5 degrees
Edgemere17.5 degrees
Double Roman22.5 degrees
Plain35 degrees

Always check the data sheet for the product itself. A roof built for one covering can sit below the minimum for another, and the pitch is measured on the roof, never read from a catalogue.

The fixings change too. BS 5534 covers the choice of batten, the method of fixing and the wind uplift calculation, so fixings are chosen per covering and per site exposure. Marley says installing to BS 5534 is not required by law, and the survey still works to it.

Slate has its own limits. Cupa, a slate maker, says BS 5534 indicates a minimum pitch of 20 degrees for natural slate at moderate exposure with a 500mm slate and a 115mm overlap, and adds that hook fixings are not to be used on any pitch under 25 degrees.

Planning, listed homes and the written quote

Planning permission is a separate test from approval. Re-roofing a house falls under Class C of the General Permitted Development Order, so in the normal case a new covering is permitted development. Flats have no permitted development rights for a new covering. A listed home needs listed building consent as well for works "in any manner which would affect its character as a building of special architectural or historic interest", and an Article 4 direction can withdraw rights in a defined area. The planning guide sets out the exceptions.

At an Arun address the council itself says replacing roof coverings on pitched and flat roofs is one of the alterations that need approval, so Arun's route is agreed with the council ahead of a re-roof.

Ask for the written quote to name the covering and to say whether a structural check is part of it. Ask the quote to confirm whether VAT and the scaffold are counted in the total price. Our guide to Building Regulations for re-roofing explains the approval test in full, and the whole job sits under new roofs.

Related questions

What if the weight difference is close to 15 per cent?

The Portal draws its line at 15 per cent or more, and Approved Document A at more than 15%. The exact figures come from the data sheets and from the roof itself, so building control gets the question before the covering is ordered, not after it arrives.

Does a heavier covering need planning permission as well as approval?

Not normally for a house, because Class C covers re-roofing. Approval under the Building Regulations is the test for a heavier covering. Listed status, flats and an Article 4 direction can each change the planning answer, so check those with the council before you order anything.