What on the roof decides the length
A roof is stripped, re-covered and finished slope by slope, so the time follows the amount of roof and the amount of detail in it. These are the points the survey weighs:
- The area to be covered, which grows with the size of the house.
- The number of separate slopes, and how they meet at hips and valleys.
- Chimneys, dormers, roof windows and walls the roof runs into, each needing its own flashing.
- Access to the roof, which means the scaffold and the space for it.
- The covering chosen, because slate and tile are laid differently.
Two roofs of the same area can take different times for those reasons, so a figure borrowed from a neighbour's job tells you little about yours. The survey records each point on the day, which means the programme is built from what is on your roof and not from an average. The survey adds what it finds on the way: rotten timber to be replaced, battens that cannot be kept, or a suspect board that has to be identified before work goes on. Our answer on asbestos found during a re-roof shows how one of those finds changes the order of work.
What can come before the first day
Some of the clock runs before the roof is touched. Each of these has its own published timing:
| Item | Timing as published |
|---|---|
| Hampshire County Council scaffold licence | Ten clear working days, counted from application to intended start |
| West Sussex County Council scaffold licence | A minimum of 10 working days' advance notice before the scaffolding is erected |
| Party wall notice, work to a party wall | At least two months, for example cutting away a chimney breast |
| Cancellation period after signing at home | 14 days, with work starting sooner only on your written request |
Timings belong to the body that publishes them, so a roofer cannot shorten them, and the dates are worked backwards from the day you want to start. A licence is needed wherever scaffolding obstructs the highway (Highways Act 1980 s169), and we arrange the licence with our scaffolder. In Portsmouth the permit goes through Colas, and Southampton City Council has a licence of its own. The answer on working in the rain and our page on cancelling a roofing contract cover two of the others.
Why the scaffold period is fixed in advance
A scaffold licence is issued for a set period, so the programme has to fit inside it. Hampshire County Council wants the whole working period asked for at the start, since extra time is handled as a fresh application with its own fees. Its fee covers the first 2 weeks, and each additional 2 week period is charged again.
West Sussex County Council licenses scaffolding by the month, and says an extension must be requested before the licence end date. Southampton City Council's licence is renewable weekly. Portsmouth's permit is charged per month on the Colas form.
The effect is the same everywhere. A job that runs over its licence period has a cost and a delay attached, so the programme is worked out before the scaffold is booked. Booking it gives the programme its first firm date, and the expected length is agreed with you before the licence is requested. It also explains why a start date can move when a licence has not come through.
The post on scaffold licences goes through each authority's rules in turn.
Weather, finds and the written programme
Weather can move a day. It belongs with the other uncertainties, and the survey cannot predict it. The same goes for finds under the old covering, such as a bat roost or an active nest. A bird's nest that is in use or being built is protected from intentional damage by the Wildlife and Countryside Act 1981, and harming a bat roost is an offence whatever the person meant to do. Work stops where that applies, and a programme that allows for such days is more use to you than one that pretends they will not happen.
That is why a quote should carry a start window and an expected length in writing, not a promise to the day. Ask what happens if the licence is late, and what happens if the strip finds rotten timber or asbestos, because each answer tells you how the programme is handled when something changes. A clear answer before you sign is worth more than a short number.
On the days themselves, our answer on living at home during a roof replacement covers what the household can expect, and the wider job is described under new roofs.