The limits that apply to a house
Part 14 Class A of Schedule 2 covers microgeneration solar PV or solar thermal equipment on a dwellinghouse. For a flat roof, development is not permitted if the highest part of the equipment would be more than 0.6 metres higher than the highest part of the roof, excluding any chimney. A pitched roof has stricter limits: no more than 0.2 metres beyond the roof slope, and no higher than the highest part of the roof. Class A also takes in a building within the curtilage of a dwellinghouse, so a detached garage with a flat roof falls under the same limits.
The same Part makes other exclusions:
- The dwellinghouse is a listed building.
- The site is designated as a scheduled monument.
- On land in a conservation area, equipment would be installed on a wall, balcony or roof enclosure that fronts a highway.
The Order also requires the equipment to be removed as soon as reasonably practicable once it is no longer needed. These limits are the starting point, not the end of the check: a survey of the roof and a look at the address decide whether any of them is in play.
Protected land and what changes there
A flat roof on article 2(3) land has an extra step. That land includes conservation areas, areas of outstanding natural beauty, National Parks and World Heritage Sites. Before beginning development there, the developer must apply to the local planning authority for a determination as to whether its prior approval will be required for the impact on the appearance of the equipment on that land.
The planning answer therefore falls into three parts:
- Outside protected land, a house flat roof can be permitted development within the 0.6 metre limit.
- On protected land, a flat roof needs that determination first.
- On a listed house, permitted development does not apply, so ask the council about listed building consent, which covers work that touches its special character.
A council that has made an Article 4 direction may have taken some of these rights away, so ask it about your address.
A block of flats has its own paragraph in the same Part, and the limits differ. Ask the council before assuming a house rule applies.
Building regulations and the roof underneath
Planning is one gate, and the Planning Portal advises discussing with the local planning authority whether all of the limits and conditions will be met. The Planning Portal says that if you wish to install a solar panel on your roof, building regulations will normally apply, and that the ability of the existing roof to carry the load of the panel will need to be checked and proven. Some strengthening work may be needed. For a Havant address, we ask your building control body about this as well, before any work is planned.
Class C of the same Order, which covers alterations to a house roof, excludes solar, so solar is judged under Part 14 rather than under re-roofing rules. Our planning guide for roof work sets out where each applies.
The Energy Saving Trust says it is important that the panels do not disturb the roof covering. On a flat roof that means thinking about how the frames are held down and where they pass through or stand on the membrane.
Keep off the roof while you look at it, because HSE's fragile-roof guidance applies: no one should step onto a roof until it has been judged safe.
The flat roof under the panels
Panels sit on a roof for a long time, so the covering beneath them is part of the decision, and a roof that will need re-covering soon is worth dealing with first. If the membrane is near the end of its published range, re-covering before the panels go on is simpler than lifting them later. Our answer on flat roof lifespans gives the sources and their disagreements.
These points are worth raising with the installer and with the roofer:
- How the frames are fixed, and whether any fixing goes through the covering.
- Who closes and makes good each penetration, and in what order the trades work.
- Whether falls and outlets stay clear under and around the frames.
- Whether the covering should be renewed before the frames go on, not after.
- Whether the roof can be surveyed before the panels are fitted, for a clean starting point.
Part L comes into it if the old membrane is replaced first, because AD L 2021 para 11.2(d) counts that as renovation, which can bring in insulation, so the order of work matters. See flat roof building regulations and the flat roofing page for the wider job.