Taking spray foam out is half the job. The timber has to be checked, the felt and battens judged and the loft insulated again. This guide follows that second half in order.

9 minute read

A page about spray foam can stop at the moment the foam comes out, as if the story ended there. For the roof the story is only half told, because the foam was covering something. Underneath are the timbers, perhaps a sheet of felt, perhaps the backs of the tiles, and none of them can be passed as sound until somebody has looked.

That is the gap this guide is about. A firm that clears foam is not always a firm that re-covers roofs, and a roof left bare in the middle of the work is a roof that can get wet. The sensible plan has the foam, the timber check, the felt and battens, the covering and the new insulation all worked out together, by people who answer for the whole roof.

We lay out the stages in order, and say where building control comes in. It belongs to our spray foam removal service, and every step can be followed on your own roof by anyone asking questions of a contractor.

Why the work after removal is the real job

The Energy Saving Trust is direct about what removal can mean: "spray foam is considered a permanent installation. If you decide to remove it at a later stage then you might also need to replace the structure it was applied to." That sentence is the reason this guide exists. Nobody knows what has to be replaced until the foam is off and the surface behind it can be examined.

RICS makes the matching point from the other side. When the timber structure is covered with spray foam, its consumer guide says, "it cannot be fully seen or inspected". Removal is the first moment at which that stops being true. A thorough look at that moment is worth more than any opinion given beforehand.

So the work after the foam is not a tidy-up. It is the inspection that the foam prevented, followed by whatever the inspection calls for. Three questions run through it.

  • Is the timber sound, and if not, which pieces need treating or replacing?
  • Is the felt behind the tiles whole and fit to stay, or does it go?
  • What goes back into the loft, and does it need building control?

An honest plan answers each of these after the foam is out, not before. Anyone who tells you the answers in advance is guessing, and a written price that pretends otherwise has hidden something. Ours arrives as a single total after the survey, and where the bare timber turns up something new we tell you before anything further is done.

The foam hid the timber. Taking it out is the first chance to look at what was underneath.

Checking the bare timber

With the foam off, we go along each rafter from the ridge to the wall plate and look at the whole surface. The checks are simple and they are done by hand and by eye, with a torch, a probe and a camera.

What we look for on the timber and what it can mean
What we seeWhat it can meanWhat happens next
Dark stainingWater has reached the wood at some timeTrace the route to the covering
Soft patch under the probeThe wood has decayed thereRepair or replace that piece
Clean, dry surfaceNo sign of water reaching itPhotograph and leave it
Foam residue on the woodSome foam has bonded to the surfaceClear it so the surface can be seen

The ends of each rafter get the closest look, at the ridge and at the wall, because a leak from above or from the wall can collect there. A timber that has been in contact with water for long is the one a probe finds soft.

The Energy Saving Trust says the rot risk behind foam depends on the type, and that it should be much lower with an open-cell foam. Whatever the foam was, we judge what is in front of us and not what the paperwork suggests. A roof that shows no staining after open-cell foam is a good result, and a roof that shows staining after closed-cell foam is a finding to act on.

Every timber gets a photograph before anything new goes over it. Those pictures are yours to keep, and they are the record that a purchaser's surveyor or lender could request.

Felt, battens and the covering

Behind the tiles or slates sits the underlay, the sheet people call felt, with the battens that carry the covering fixed across the rafters over it. Foam applied from the loft side can reach the back of the felt, and in a roof with no felt it can reach the backs of the tiles themselves. Once the foam has gone, each of the three is judged on what it shows.

  1. The felt: where it comes away whole and sound, it can stay. Where it is torn, perished or bonded to foam residue, it goes.
  2. The battens: where they are sound they stay. Where they have been marked by water or damaged by the removal, they are renewed.
  3. The covering: tiles or slates lifted for the work are refixed where they are sound and replaced where they are not.

Some of this work can be done from the loft, and some cannot. Where foam has locked itself around battens or tile backs, the clean way to free them is to lift the covering from outside. That is where scaffold comes into it, and where the weather matters, because a slope that is open has to be closed again at the end of each working day.

New felt is dressed into the gutter at the eaves, and it should lap properly. That detail is what carries the rain safely out of the roof, and it is where the route of the water ends. The other places along it, ridge, valleys and flashings, get the same look as they would on any roof.

The written price for all this is one total. It names what is to be renewed on the day, and it states whether scaffold is included, so you know what you are agreeing to before work starts.

Re-insulating, and what Part L says

When the foam goes, the loft loses its insulation, so a plan for the new one is part of the job. Part L of the Building Regulations (conservation of fuel and power) sets the energy rules, and for houses in England the document is Approved Document L, Volume 1. Its 2021 edition applies until 24 March 2027, when the 2026 edition takes over for work of this kind.

Until then, Table 4.3 of AD L 2021 gives 0.35 as the threshold for a retained roof and 0.16 as the improved figure a renovated roof works to, if that is feasible and pays back within 15 years. Paragraph 11.3 explains when a renovation triggers the requirement for the whole element: where more than 50% of the surface of the roof is renovated, or where the work counts as a major renovation, which is more than 25% of the external envelope.

AD L 2021 figures for a renovated roof
ItemFigure
Threshold for a retained roof (Table 4.3)0.35 W/(m²·K)
Improved figure (Table 4.3)0.16 W/(m²·K)
Payback test (para 4.13)15 years or less
Renovation trigger (para 11.3)More than 50% of the surface

Those are the figures the document gives, and they are not a design. What goes into your loft depends on the roof, and which insulation suits it is a separate choice from taking the foam out. Our short answer on what to insulate with after spray foam covers the options.

Your building control body will say whether an application is required, and either the council's team or a registered approver can take it.

Who does what, in what order

The gap this guide started with is a gap between trades. Removal, timber repair, roofing and insulation can each be done by someone different, and each can leave the roof in a state the next person has to work out for themselves. The job goes best when one party plans the order and answers for the roof at the end of every day.

  1. Survey: the roof from outside, the loft from the hatch and any paperwork on the foam.
  2. Clearance: the loft emptied and a safe way in made, then the foam taken out.
  3. Timber check: every rafter looked at and photographed, with findings reported to you.
  4. Repairs: any timber treated or replaced, then felt and battens renewed where needed.
  5. Covering: tiles or slates put back or replaced, and the eaves dressed into the gutter.
  6. Insulation: the new loft insulation fitted to the agreed plan, with any building control step done.

The survey comes first on that list, and no slope is left open overnight. The Energy Saving Trust's warning about replacing structure is the reason: you want to find out what the job really involves before you commit to it.

MyJobQuote's average cost of spray foam removal is a figure for the removal stage, quoted at £40 per m², and it does not describe the felt, battens or insulation that follow. We do not use it to price your job. Our spray foam removal cost guide explains the figure, and our own price is the written total after the survey.

Keeping a record of the work

A roof that has had foam removed has a history worth keeping. A purchaser, a surveyor or a lender may ask for it, and it is far easier to collect as the work happens than to rebuild from memory years later.

  • Photographs of the foam before removal, from the loft hatch and from inside the roof space.
  • Photographs of the bare timber, each rafter, before anything new was fitted.
  • The written price and the description of what was done.
  • Any building control paperwork, if an application was needed.
  • Details of the new insulation: the product, its thickness and where it was fitted.

RICS reported in March 2023 "concern within specific sectors of the lending market, such as equity release mortgages", and it advises checking with a mortgage provider about foam. We cannot speak for a lender. What we can do is hand over a record that shows what the roof looked like under the foam and what was done about it.

If you are selling, share the record early, since a buyer's surveyor may ask for exactly this. If you are staying, it still has value, because the next person to work on the roof will be glad of photographs of timber they cannot otherwise see.

When the work ends, the site is left clean, the loft is clear and you hold the folder. If something in the folder is missing, ask for it before the last day.

Ask about your roof

Questions about the work after foam

Who checks the timber once the foam has gone?

It should be the roofer who will answer for the roof, looking at every rafter while the surface is bare and photographing it before anything new goes on. RICS says covered timber cannot be fully seen or inspected, so this is the first real chance. We report what we find, and tell you before anything further is done.

Do I have to reach 0.16 when I re-insulate?

AD L 2021 expects a renovated roof to work to the improved 0.16 W/(m²·K) of Table 4.3, against a threshold of 0.35, where that is feasible and pays back within 15 years. It is a test of what is feasible, not a flat demand. Your building control body will tell you how it applies to your work.

What should I keep when the work is finished?

Keep the photographs of the foam and the bare timber, the written price and description of the work, any building control papers and the details of the new insulation. A buyer's surveyor or a lender may ask for them later, and the Energy Saving Trust describes foam as a permanent installation, so the record is part of the roof's history.