Replacing a Velux window like for like: what it involves

A like-for-like Velux swap reuses the opening already in the roof, so the job is the window, its flashing and the covering around it.

9 minute read

Swapping an old Velux window for a new one of the same size sounds like a small job, and in building terms it is smaller than cutting a new opening. The rafters, the framing and the hole itself are already there. What remains is everything that keeps rain out of that hole: the frame, the flashing that leads water over the covering, the underlay behind it and the tiles or slates around the edge.

Rain still arrives at the head of the frame and has to be led down both sides and across the foot, so a swap is judged on those four edges and not on the glass. This guide covers what counts as like for like, what is read before anything is ordered, the order of work, the flashing, the energy and escape checks, and the published costs.

If the window you want is bigger or sits somewhere new, you are cutting a fresh opening, and our roof windows and skylights page covers that work. Everything below assumes the same place and the same size.

What counts as like for like

Like for like means the new window goes into the same opening, at the same size, in the same slope. If any of those three changes, the job is no longer a swap, because the structure and the covering around the opening change with it.

How far each change takes the job from a straight swap
ChangeWhat it brings in
Same size, same positionA new frame, a flashing kit and the covering relaid at the edges
Wider or tallerA larger hole, with rafters cut and short cross timbers fitted to carry them
Higher or lower on the slopeA fresh opening, with the old one closed and covered to match
A rooflight on a flat roofA kerb and a flat-roof waterproofing detail, a different job from a slope window

MyJobQuote prices the straightforward case lower. It says a Velux window replacement costs around £100 less for a straightforward swap, as the opening is already in place. The figures are in the last chapter.

Sometimes the survey finds an opening that is not fit to reuse, such as softened timber round the frame. That turns a swap into structural repair first, and you hear it before any price is written.

That is why the survey starts by asking what you want from the new window. Fewer drips and a clear view out suit a swap. More light, more headroom or a second window suit a different job, and it is better to know that before the price is written, since a swap quoted first and enlarged later changes both the structure and the total.

The opening is already cut, so the work is closing its four edges again.

Reading the old window before anything is ordered

The old window tells the survey what to order. Some of it is read from the loft, some from the roof, and some can be photographed from the room before anyone visits. These are the points that matter.

  • The outside dimensions of the frame, measured to its edges, since the new window has to suit the opening that exists.
  • The kind of covering around it, because a flashing kit is made for one kind, such as profiled tile, flat tile or slate.
  • Any maker's label on the frame or sash, photographed, which can help a supplier match the unit.
  • The timbers round the frame in the loft, whether they are dry and sound or stained and soft.
  • The underlay and the lining where they meet the frame, looking for old tide-marks.
  • How the sash opens and closes, and any corner where it sits out of square.

Take photographs in daylight: one of the whole slope from the garden or street, and one close-up of the frame taken from the room side. Please keep off the roof itself and photograph it from the ground. Say whether the loft can be reached, since the frame is released from inside as well as out.

A window that mists between the panes may need only a new glazing unit, and a leak at the edge of the frame points to the flashing. The survey separates the two, so the money goes on the part that failed.

The order of work, from old frame to new lining

Work follows the route of the rain, so the layers go back in the order water meets them: the covering above, the flashing, the frame, and the lining on the inside. For a straight swap the sequence runs like this.

  1. Cover the floor and furniture below, and clear the loft space beside the opening.
  2. Lift the covering and the old flashing around the frame, setting aside any tiles or slates that can go back.
  3. Release the old frame from the rafters and lift it out of the opening.
  4. Check the exposed timbers and the underlay at the edge of the hole, and repair or replace anything damaged.
  5. Fix the new frame in the same position and set it square.
  6. Fit the flashing kit for your covering, following its instructions, so each lap sheds water outwards.
  7. Relay the covering up to the flashing, line the opening inside, and clear the site.

The opening stays uncovered only for as long as the swap needs, and the day is chosen with the weather in mind. Scaffold is part of the single price. When a highway licence is needed, we arrange the licence with our scaffolder.

Step four is where a swap can change shape. A damp rafter or perished underlay found at that point is dealt with there and then, because closing it up again would hide it. You are told what was found, with a photograph, before the new frame goes in.

The flashing and the covering around the frame

The flashing is the metal or moulded kit that joins the frame to the covering. It has to lead water down both sides and over the covering below, so that none reaches the gap between frame and rafters. Kits are made for particular coverings, and our answer on what a flashing kit is and which one you need explains the choice.

A new frame set into an old flashing puts a new part into old trouble. The same goes for the covering. If the tiles or slates around the window have slipped or cracked, a new window in the middle of them inherits the same route for water to get behind the flashing, so the survey looks at the surround as well as the glass.

Each edge has its own check once the frame is in.

  • The head, where the water from the whole slope above arrives and is split to both sides.
  • The sides, where it runs down past the frame and has to stay on top of the flashing.
  • The foot, where the flashing has to lap over the covering below and not tuck beneath it.
  • The corners, where two lengths of flashing meet and are least forgiving of a cut made short.

Moss, leaves and grit collect at the head of a frame. The surround is cleared while the covering is open, so the new frame does not start with a dam of debris sitting behind it.

Sealant alone does not stand in for any of these laps. It can close a hairline gap for a time, and it can hide a missing lap, so ask what is under any bead you are shown.

Energy and escape checks on a swapped window

Until 24 March 2027, AD L 2021 Table 4.2, headed "Limiting U-values for new fabric elements in existing dwellings", sets 1.4 W/m²K or Window Energy Rating Band B for roof windows. Its note says the window row includes roof windows, and 2.2 W/m²K is the rooflight figure only. Ask the supplier which figure the unit you are offered carries, and ask building control how the table applies to your swap. Building control is carried out by the council's building control team or by a registered building control approver. Our guide to roof window energy rules sets out the figures in full.

If the window lights a loft bedroom, check whether it is also the way out. Approved Document B para 2.10 describes an escape window as having:

  • "A minimum area of 0.33m2."
  • "A minimum height of 450mm and a minimum width of 450mm", the route through the window being allowed to run at an angle.
  • The bottom of the openable part, which must be "a maximum of 1100mm above the floor".

Escape windows cover storeys up to 4.5 m above ground, and a window lighting a higher storey raises a different question, covered in our answer on a roof window as a fire escape. Measure the openable part of the new unit against these figures before you order, not after it is fitted.

A swap that changes the opening's shape, even slightly, can change these numbers, so the dimensions go on the order in writing and are checked again when the new unit arrives.

Published costs, permissions and the written price

Published guides give the scale, not your price. Two third-party figures apply to a Velux window.

Published figures for a roof window swap
SourceFigureWhat it says
MyJobQuote, September 2026£1,100Average cost for a standard mid-range Velux window, and around £100 less for a straightforward swap. No VAT basis is stated.

Checkatrade's repair-rate table, dated June 2026, has a line for replacing a rooflight, a Velux for instance, from £1,000. That is a starting figure and not an average, and the table says its costs are exclusive of VAT. Ask any quote you receive to say whether VAT is in the total.

Our quote comes as one written total when the survey has been done. It should say whether scaffold and VAT are included, whether the flashing is renewed, how the covering round the frame is dealt with and who makes good the ceiling lining. The rest of the price depends on the covering, the access and the state of the timbers, which only the survey can see. Our guide to how much a Velux window costs goes further into what moves the number.

Being listed leaves permitted development for roof work in place and puts listed building consent on top of it wherever the work touches the building's character. In a conservation area an Article 4 direction can remove further rights, and a flat has no permitted development rights for roof work. The side-slope glazing condition and the other limits on roof alterations are in our planning guide.

Ask about your roof

Questions on swapping a roof window

Do I need permission to swap a roof window like for like?

It depends on the house. A listed home keeps permitted development for roof work but needs listed building consent as well where the work would affect its character, and a flat has no permitted development rights for roof work. Our planning guide sets out the tests, and the council for your address has the final word.

Does a like-for-like swap cost less than a new opening?

MyJobQuote's average for a standard mid-range Velux window is £1,100, and it puts a straightforward swap at around £100 less because the opening is already there. Treat both as published averages that cannot see your roof. Our quote follows a survey and gives one written total.

Can the new window be larger than the old one?

A larger window is no longer a swap. The opening has to be enlarged, which means cutting into rafters, fitting short cross timbers to carry the load and relaying the covering round the bigger hole. The survey measures the rafters from the loft first, and the written price then spans the full job as a single total.