A U-value measures how quickly heat passes through part of a building, written in W/m²K, and a lower figure loses less heat. Approved Document L is where the Building Regulations cover fuel and power in a home. It sets a limit for each part of a roof, and the limit for a roof window differs from the limit for a rooflight and from the limit for the roof itself.
This guide applies to dwellings in England, which covers every address we work at. It gives the figures in AD L 2021, the renovation triggers that decide when a whole roof is brought up to the improved figure, the change due on 24 March 2027, and how building control comes into it. Each figure carries its table or paragraph number so that you can check it.
Where the question is a straight swap of one window for another, our guide to replacing a Velux window deals with the work itself.
Which figure applies to which part of the roof
AD L 2021 takes effect "on 15 June 2022 for use in England". Its Table 4.2 is headed "Limiting U-values for new fabric elements in existing dwellings", and it is the table to read for a new window, a new rooflight or a new roof.
| Element | Limit |
|---|---|
| Roof | 0.15 W/m²K |
| Window, including roof windows | 1.4 W/m²K or Window Energy Rating Band B minimum |
| Rooflight | 2.2 W/m²K |
The note on the window row reads "Including roof windows and curtain walling". A roof window therefore takes the window figure, and 2.2 W/m²K belongs to rooflights only. The Building Regulations themselves say the same thing from the other side: a thermal element "means a wall, floor or roof (but does not include windows, doors, roof windows or roof-lights)". Glazed parts are treated as windows, and the roof is treated as the roof.
The table lists rooflights on their own row, so one figure cannot stand in for the other. Because these figures are limits, the product's own figure has to be the same or lower. A higher figure loses more heat and falls outside the limit. The roof figure of 0.15 is the one for a roof built as a new element, and Table 4.3 below is the one for an existing roof that is only being renovated.
The full text of the document is on GOV.UK, where each number above can be found.
Glass is judged as a window, and the roof around it is judged as a roof.
Reading the window row for a roof window
The window row offers two ways to comply: a U-value of 1.4 W/m²K, or Window Energy Rating Band B as a minimum. Window Energy Rating, shortened to WER, is a banding rather than a U-value, so the two are different measures and a product is offered on one or the other.
The mistake to look for is the wrong row. A rooflight at 2.2 W/m²K is not a roof window at 1.4 W/m²K, and a quote that quotes the 2.2 figure for a roof window should be questioned.
When a window is quoted, ask for these in writing.
- Which of the two the maker calls the unit, a roof window or a rooflight, so you know which row it belongs to.
- The U-value, or the WER band, that its maker gives for the exact size and glazing you are buying.
- Where the paperwork can be seen if building control asks for it.
- Whether the figure is for the glazing alone or for the whole window, since the table limits the window.
Keep the supplier's data sheet and the invoice with the date of the work, since building control may ask for them. The row says "minimum", so Band B is the lowest band allowed and not a target to stop at.
Brochure names vary from maker to maker, so rely on the category the table uses and not on the product name.
None of that needs a calculation on your part. It needs a supplier who states the figure against a size, and a roofer who keeps the paperwork with the job.
When the roof itself is renovated: Table 4.3
Table 4.3, "Limiting U-values for existing elements in existing dwellings", is the one for a roof that already exists and is being worked on. Its roof line has two columns: a threshold of 0.35 and an improved figure of 0.16 W/m²K. Paragraph 4.12 says renovated elements "should achieve the U-values in Table 4.3, column (b)", the improved column.
What counts as renovation is set in paragraph 11.3. The whole element is improved where either of these applies:
- "More than 50% of the surface of the individual thermal element is renovated."
- The work is a major renovation, which is "when more than 25% of the surface area of the external building envelope is renovated."
Paragraph 11.2(d) lists "Replacing the waterproof membrane on a flat roof" as renovation. In plain terms, if more than half of a roof is renovated, AD L expects the whole roof to be brought up to the Table 4.3 standard where that is feasible.
The Planning Portal's re-roofing guidance uses similar numbers for a different question, namely whether a building regulations application is normally needed. It says none is normally needed if less than 25 per cent of the building envelope and less than 50 per cent of the roof is affected. Because the two sets of numbers sit side by side, ask building control which route applies to your job instead of assuming one answers the other.
Once more than half of a roof is renovated, AD L looks at the whole roof.
Loft conversions, and when the improved figure cannot be reached
Paragraph 4.12 also covers retained roofs. A retained element above the threshold, "for example through a loft or garage conversion", should be upgraded to Table 4.3 column (b). So where a loft conversion keeps the existing roof and its U-value is above the 0.35 threshold, the roof should be upgraded to 0.16 W/m²K, and a roof window put into that roof takes the window row from Table 4.2.
The improved figure is not demanded at any cost. Paragraph 4.13 is the fallback. Where column (b) "is not technically or functionally feasible or" "would not achieve a simple payback of 15 years or less", the roof is upgraded to the lowest U-value that satisfies both of these tests:
- is technically and functionally feasible, and
- can achieve a simple payback not exceeding 15 years.
The same paragraph adds that, generally, a thermal element once upgraded "should not have a U-value greater than 0.7W/(m2·K)".
That is a judgement made on the facts of your roof, which is why it is worth raising at the survey. If a roof has little depth for insulation, or the insulation would take away the headroom that the conversion is meant to create, the survey records that, and the figure that follows is the best feasible one inside the payback limit.
Escape from a converted loft is a separate rule set, covered in our answer on a roof window as a fire escape.
24 March 2027: when AD L 2026 takes over
A new edition is on its way. AD L 2026 says it "takes effect on 24 March 2027 for use in England" for work outside the higher-risk category. For higher-risk building work the date is 24 September 2027. Until 24 March 2027, AD L 2021 is the document to work to, and every figure on this page comes from it.
The dates above are the ones each document gives for itself. Which edition a particular project falls under, if it straddles the changeover, is a question for building control and not for a guide.
The tables are renumbered in the new edition. The table for new elements in existing dwellings becomes Table 3.2, and the table for existing elements in existing dwellings becomes Table 3.3.
- Before 24 March 2027: Tables 4.2 and 4.3 of AD L 2021.
- From 24 March 2027, for work outside the higher-risk category: Tables 3.2 and 3.3 of AD L 2026.
- For higher-risk building work: the new edition from 24 September 2027.
The 2026 figures are not restated here, since they only matter once the edition applies. The text is already published on GOV.UK if you want to read ahead.
If your order might fall on either side of 24 March 2027, ask the quote to name the edition it is working to.
If your work is planned across the changeover, the date that counts is a question for your building control body, and it is worth putting to them before the order is placed and not after the window is on site.
Building control, consents and the written price
Building control is carried out by the council's building control team or by a registered building control approver. Under the registration regime that began on 6 April 2024, a private business doing that work has to register with the Building Safety Regulator. For Havant addresses, we confirm the building regulations route with your building control body before work starts, and for other councils we put the same question to the building control team for the address.
Energy figures sit beside consents, and they do not replace them. A window that meets Table 4.2 in a listed house may still need listed building consent where the work touches what is special about the building. In a conservation area an Article 4 direction can remove permitted development rights. A flat has none for roof work. Our planning guide sets out the tests.
Our written quote gives one total price once we have surveyed. It should say which window row or table the work is being done to, whether scaffold and VAT are included, and what happens to the ceiling lining. For the work around a new unit, see our answer on building regulations for a new roof window, and for the wider service, our roof windows and skylights page.
Where a listed building or a conservation area is involved, the council's planning team is a separate call from building control, and both answers are wanted before an order is placed.