023 9396 0313 Get a written quote

Lead codes

What lead code is used for flashing?

The short answer

Royston Lead's cast-lead brochure lists codes 4, 5 and 6 for flashings: code 4 is 1.80 mm thick, code 5 is 2.24 mm and code 6 is 2.65 mm. The brochure recommends code 3 for lead soakers only. It does not name one code as right for every flashing, so the specification for the job picks the code for each detail, and a quote should say which one it names.

Lead arrives on site as numbered rolls, and the number gives the thickness. Which codes are listed for flashings and who picks between them.

Leadwork on a pitched roof

What the number on a roll tells you

Each code stands for one thickness of cast lead sheet. The higher the code, the thicker and heavier the sheet. Each code also carries a colour mark, so a roll of code 4 is blue, code 5 is red and code 6 is black, which lets the rolls be told apart in a stack at the supplier's yard or on a scaffold.

For each code the brochure prints a thickness in millimetres and a weight per square metre. Code 4 weighs 20.41 kg per square metre, code 5 weighs 25.40 and code 6 weighs 30.05. Moving up a code therefore puts more lead on the roof, and a heavier sheet to lift, carry and dress into shape.

The brochure also shows where each code is used, with a key that runs from A to E. Soakers are A and flashings are B, followed by three more groups of heavier details, valley and parapet gutters and dormers among them. A code is marked against every group it suits, and several codes appear against more than one. That is the reason the question has several entries in its answer, and the reason a roofer reads the detail on the roof before ordering anything.

The six codes side by side

The table sets out all six codes, with the kinds of detail the brochure lists for each one.

Lead sheet codes in Royston Lead's brochure
Code and colourThicknessDetails it is listed for
3, green1.32 mmSoakers only
4, blue1.80 mmSoakers, then flashings, a pitched valley and dormers
5, red2.24 mmDormers, parapet and box gutters, valleys and flashings
6, black2.65 mmDormers, parapet and box gutters, valleys and flashings
7, white3.15 mmValleys, parapet and box gutters and dormers
8, orange3.55 mmValleys, parapet and box gutters and dormers

Flashings appear against codes 4, 5 and 6 only. Codes 7 and 8 are listed for the heavier gutter details and for dormers but not for flashings, and code 3 is marked for soakers alone. The thickness of each code is the one printed in the brochure, and the weights quoted in the section above come from the same table. The brochure is a supplier's catalogue of cast lead, so it is a guide to the range on sale and not a rulebook for a particular roof; the specification for the job remains the final word on what goes where.

Who picks the code for a flashing

The brochure lists what each code is used for, and the job's specification then fixes the code for each detail. Its table does not put codes 4, 5 and 6 in an order of merit for flashings, and it does not say a thicker sheet is always the better one. No rule such as "code 5 for every stack" is offered here, and none should be accepted from a web page that has never seen your roof.

What we can describe is how the choice is reached. The detail on the roof is looked at first: how long the run is, whether it sits at a stack, a wall or a dormer, and what it has to lap over. The code is then taken from the specification for that detail. Where the job is to match old work, the old lead is examined as well, and any difference is noted on the quote.

A lead flashing also sits outside the flat-roof standard. BS 6229:2025 deals with continuously supported flexible waterproof coverings, which means membranes, so lead sheet is not within its scope. Why thickness and movement matter together is explained in our answer on why lead splits on a roof.

What a quote should say about the code

A written quote for leadwork should name the code for each detail it covers, because that single word tells you whether the lead being fitted suits the job. Look for these points:

  • the code stated for each flashing, with a separate code for any soakers
  • the code for any valley, parapet or box gutter in the same job
  • whether old lead is being replaced like for like, or whether the code changes
  • whether the pointing and wedges are renewed with the new lead
  • whether any scaffold is included in the price

If a quote says only "lead", ask which code it means. Anyone who has surveyed the roof should be able to name it, and to say why it suits that detail rather than a lighter or heavier one.

Our answer on soakers and stepped flashing shows where each piece sits at a wall, and the lead roofing page covers the rest of the work. After the survey, our quote is a single written total, and it names the lead it relies on, so that you can compare it with another quote like for like.

Related questions

Is code 4 lead thick enough for a chimney flashing?

Royston Lead lists code 4 for flashings, alongside codes 5 and 6, so it sits within the brochure's range. Which code a chimney needs is a question for the specification for that detail. Ask the roofer to name the code on the quote and to explain why it suits the stack.

Why is code 3 lead only used for soakers?

Royston's brochure recommends code 3 for lead soakers only, and marks it against no other detail. It is the lightest sheet in the range. If old work includes a flashing made from lead of that colour and thickness, it is a mismatch, and a roofer should look at it.

Where's the water showing?

You'll get one written total price.

10-year workmanship guarantee, in writing