What the 80 year figure covers
The figure comes from MyJobQuote's guide to replacing leadwork on a chimney, which was updated in September 2026. Its wording is that lead flashing that is correctly installed can last for over 80 years. Two things in that sentence are easy to lose when it is repeated.
The first is the phrase can last. It describes what the material is able to do, not what every roof will see, and it is not a minimum. Plenty of lead outlives its mortar joint or its fixings and then needs repair well inside that span, and some will go on beyond it.
The second is the phrase correctly installed. Lead sheet is soft and is dressed by hand into the brickwork and the covering, so the quality of the fitting counts for as much as the metal. A thin code on a long run, or lead nailed so tightly that it cannot move, belongs to the cases where the figure does not apply.
The figure is about flashing, which is the lead that closes a joint at a wall or a stack. It is not a figure for a whole lead roof.
Other published figures for lead
Other guides give lead lifespans too, and they do not match: they are given for different subjects, and none of them explains the gap. Read each as a typical range, never as a date on which anything fails.
| Source | Figure | What it describes |
|---|---|---|
| MyJobQuote | Can last for over 80 years | Correctly installed lead flashing |
| HomeBuilding | 60 to 100 years | A lead flat roof, approximate |
| Less | 50 to 100 years | Lead as a flat roof material |
HomeBuilding's guide was last updated on 30 September 2025, and Less's guide on 27 October 2026. Because the three describe different things, they should not be set against one another as if one were right and the others wrong. A flat roof carries water over its whole surface, while a flashing sits at one joint, so the two meet very different demands.
None of the three says what will happen to your lead. They are a guide to the scale of time involved, and the reason a good flashing is often worth repairing in place and not stripping out. The state of the sheet, its fixings and its joint is read on site, by looking at it, which no published table can do for you.
What can shorten a flashing's life
Lead need not wear out evenly. When a flashing fails early, the cause can be one of a few details that a survey can check:
- Movement that has nowhere to go, such as a long run, tight fixings or a lap that cannot slide, which is how splits start.
- A code of lead too light for the detail. Royston Lead's brochure recommends code 3 for soakers only, so a flashing cut from it is a fault we look for.
- Mortar that has crumbled around a sound sheet, leaving it loose in its joint.
- Wedges that have dropped out, so the lead can lift in the wind.
- Leaves and debris left to sit in a valley or behind a stack.
- Old sealant smeared over a failing joint, which hides what is happening underneath.
Several of these concern what surrounds the lead and not the lead itself, so the pointing can call for work long before the sheet does, and a repair to it is a fair part of the job. Our answer on why lead splits follows the movement point further.
Judging the lead you have now
Age alone does not settle whether old lead needs replacing. Grey, weathered lead that lies flat, is held tight in its joint and shows no cracks may have many years left, and replacing it would give no benefit. A newer flashing with a split or a lifted step may need work at once.
Standing in the garden, you can look for lead lifted clear of the brickwork, crumbs of mortar or small wedges in the gutter, cracks across the grey, and sealant or tape smeared over a joint. Indoors, a mark on a ceiling or breast wall that returns after rain suggests an open joint. Take dated photographs, which help whoever surveys it, and do not climb up to look.
At the survey we say whether the lead calls for repair or for renewal and explain why, and a sound repair is offered before a new sheet. Our guide to lead flashing repairs sets out the choices, and what leadwork costs covers the published prices. All of our lead roofing work starts from a look at the joint.