Sheet lead is supplied by code, with each code standing for one thickness. Thicker sheet weighs more and is stiffer to dress into place, so the choice has to match the task: a narrow strip that only tucks under a tile is not the same task as a channel that carries the rain off a whole roof slope. The number in a quote should therefore come with the detail it applies to.
A cast lead brochure from Royston Lead sets out codes 3 to 8 with their thickness, weight, colour and the details each is used for. It explains those details in plain words, shows where each sits on a roof and closes with the questions worth asking when a quote names a code.
What a lead code actually tells you
Each code is a number from 3 to 8, and a higher number means thicker, heavier sheet. The Royston Lead brochure gives every code a thickness in millimetres, a weight in kilograms per square metre and a colour. The colours run in a fixed order from code 3 to code 8, so a code can be matched to its sheet.
The table reproduces the brochure's figures:
| Code | Thickness (mm) | Weight (kg per m²) | Colour |
|---|---|---|---|
| 3 | 1.32 | 14.97 | Green |
| 4 | 1.80 | 20.41 | Blue |
| 5 | 2.24 | 25.40 | Red |
| 6 | 2.65 | 30.05 | Black |
| 7 | 3.15 | 35.72 | White |
| 8 | 3.55 | 40.26 | Orange |
Read down the columns and the pattern is plain. The thinnest sheet, code 3, is just over a millimetre thick. The thickest, code 8, is over three and a half. The two figures rise together at every step, which is why the brochure can pair a code with a detail.
The gaps between codes are modest. From code 4 to code 5 the sheet gains 0.44 mm, and a square metre gains about five kilograms. Those small steps are why the code matters: a roofer choosing between neighbouring numbers is choosing a slightly heavier, slightly stiffer sheet, and the detail decides whether that is needed.
It is also worth noticing how much metal is involved. A single square metre of code 5 weighs 25.40 kg, so lead laid over a large area, such as a long valley or a flat porch roof, adds up quickly, and that is one more reason the code is chosen with care.
Which details each code is used for
The brochure carries a second table that says what each code is used for. It sorts roof details into five groups: soakers, flashings, pitched valley gutters, parapet, box and tapered valley gutters, and dormers. Reading across from the codes gives this:
- Code 3 is recommended for lead soakers only.
- Code 4 is listed for soakers, flashings, pitched valley gutters and dormers.
- Codes 5 and 6 are listed for flashings, pitched valley gutters, parapet and box gutters, and dormers.
- Codes 7 and 8 are listed for pitched valley gutters, parapet and box gutters, and dormers.
Two things stand out. The thin end of the range is limited, since code 3 is recommended for soakers and nothing else. And the thick end has no flashings in it: the heaviest codes are the ones listed for the channels that gather the most water.
The brochure comes from a lead supplier and covers cast lead sheet, so it shows how that supplier sorts its codes. It is not a rulebook for every roof. The brochure leaves the final choice to the specification, which is the point the fifth section comes back to.
A roofer reading the list should treat it as a starting place, then compare it with the detail in front of them. The width of a channel, the height of an upstand and the exposure of the roof all change the answer, and none of them appears in a table of codes.
Soakers and flashings: where wall meets roof
Two of the five groups sit where a roof meets something upright, such as a chimney, a party wall or the cheek of a dormer. Rain runs down the slope and arrives at that junction, and without a metal layer it would run behind the wall instead of past it.
A soaker is a little square of lead folded into an L. One arm sits flat beneath a tile or slate and the other turns up against the wall. Every course along the junction gets its own soaker, so the pieces climb the slope together and pass the water out onto the covering below. Code 3 is the one the brochure recommends for this.
A flashing is a single strip of lead dressed over the upturned edge of the roof covering and pushed into a slot chased out of the brickwork, or fixed to the wall face. It does the work of the many small pieces in a soaker system. In the brochure, code 4 and codes 5 and 6 cover flashings.
Where the lead has to turn a corner
At a junction the water route is easy to follow, and the lead is the one part of it that has to turn a corner without leaving a gap. Our guide on lead flashing repairs covers what goes wrong at these junctions and how it is put right.
Soakers sit out of sight once the roof is finished, so a faulty one is found by its effect indoors, which is why a survey looks at the ceilings below as well as the lead.
Valleys, parapets, box gutters and dormers
The remaining groups are the ones where lead acts as a channel rather than an edge. Each moves water along a line, so each has more water to deal with than a flashing, which is why the thick codes appear in these groups.
Pitched valley gutters
A pitched valley is the sloping channel formed where two roof planes meet in an internal angle. Lead lines the channel, and the rain from both planes runs down it towards the gutter below. Codes 4 to 8 are all listed for this detail.
Parapet, box and tapered gutters
A parapet gutter runs behind a low wall at the edge of a roof, and a box gutter sits between two slopes or beside a wall. A tapered valley gutter is made to a gradual slope so that the water drains out. These are flat or near-flat channels, and codes 5 to 8 are listed for them.
Dormers
A dormer is a small structure standing out from the roof slope, with its own cheeks, roof and junction back to the main slope. The brochure lists codes 4 to 8 for dormers, since one dormer can contain flashing, soaker and gutter details together.
Our guide on lead valleys explained covers the first of these in more depth.
In every one of these channels, the quality of the joint and the fall of the lead count as much as its thickness. A thick sheet laid without a fall holds water, and the code cannot fix that.
Why the specification sets the code
The brochure itself leaves the code to the specification for each detail. That is the limit of any table: it tells you what a supplier lists for a detail, and it does not tell you what your roof needs. The width of a valley, the length of a run, the exposure and the age of the structure all feed into the choice, and they are the reason a survey comes before a code.
One thing worth knowing is what the standards do not cover. BS 6229:2025, the current British Standard for flat roofs, deals with roofs finished in membranes; lead sheet falls outside it. A quote that leans on that standard to justify a lead code is reaching for the wrong document, so ask which specification the code comes from.
Lead has a long working life when it is installed well. MyJobQuote says lead flashing that is correctly installed can last for over 80 years. That is a figure for flashing, and it depends on the word correctly: the dressing, the fixing and the condition of the wall behind all count alongside the thickness.
A flashing can also reach into a neighbour's wall. Section 2(2)(j) of the Party Wall etc. Act 1996 lets a building owner cut into the neighbouring building in order to fit a flashing or other weather-proofing. Our answer on party walls and lead flashing sets out the notice rules.
Listed houses
On a listed house the position is different again. Listed building consent covers anything that touches the special character of the building, so a change of metal or of detail on a protected roof goes to the council first and the roofer second, and that answer should be in hand before any code is chosen.
Questions to ask when a quote names a code
A code in a quote is worth having, since it means someone has thought about the metal. It is worth more when it comes with the reason. A quote that names a code, a detail and a location lets you check what you are paying for, and a quote that just says lead does not.
These questions make a leadwork quote easier to compare:
- Which code is proposed for each detail, and where does it go?
- Is the lead replacing a failed piece, or is it a new detail altogether?
- Are the walls and the chimney being checked behind the lead as well?
- Does the wording state if VAT and scaffold are inside the total?
- Is the total written down?
Cost figures for leadwork are third-party averages. MyJobQuote (September 2026) gives around £200 for a chimney lead flashing patch repair and around £570 for a full replacement, and puts a full leadwork replacement somewhere between £350 and £920, depending largely on whether scaffolding is required. Checkatrade (June 2026) gives lead flashing repairs at £50 to £70 per metre. Each is one cost guide's average, makes no allowance for your roof, and is not one of our prices.
Ours is a single written price, following a look at the roof itself. The full range of leadwork we carry out sits under lead roofing and leadwork.
If a quote names a code that you cannot match to a detail, ask for the detail to be added in writing before you accept it. Lead is a material where the specification matters, and a written specification is the simplest thing to hold the work against afterwards.
Filed under Lead roofing