Replacing a polycarbonate conservatory roof with a solid one is a common wish, and the Planning Portal says why: "Many homeowners choose to replace their traditional polycarbonate conservatory roof with a solid tiled roof for better thermal efficiency." The same page then gives the rule that decides the job: "A new roof must comply with building regulations to ensure it is structurally safe, energy efficient and properly ventilated."
That sits oddly beside the fact that conservatories can be exempt from the energy requirements. The two are not in conflict. The exemption belongs to the conservatory as it was built, and it is conditional. A new roof is new work, and the conditions have to be checked again before it goes on.
This guide covers England only. It takes the exemption condition by condition, explains the weight question that comes with a heavier roof, sets out who checks the work and gives the third-party costs and lifespans that sit around the decision. Your written price comes after a survey, as one total.
What the Planning Portal says about a new roof
The Planning Portal's answer to the question of changing a conservatory roof is short, and it is worth reading closely. It does not say that every conservatory roof needs formal approval. It says a new roof "must comply with building regulations", and it gives three reasons: the roof has to be structurally safe, energy efficient and properly ventilated.
Those three words map onto the three questions we ask at a survey.
- Structurally safe: can the frame, the dwarf walls and the foundations carry the new roof, and is it fixed to the house wall in a way that holds?
- Energy efficient: does the conservatory keep its exemption, or does the new roof bring the energy requirements into play?
- Properly ventilated: does the new roof leave the room with the ventilation it needs?
Compliance is shown to building control. Building control is carried out by the council's building control team or by a registered building control approver, and it is separate from planning. In Havant, we confirm the building regulations route with your building control body before work starts, and in other areas we ask the body for that address.
The Portal also keeps two questions apart that people mix up. Planning permission is one regime and building regulations another, and a roof can satisfy one while the other is still open. If the answer to any of the three questions above is uncertain, the survey says so and the price waits.
Nobody should treat a quoted line from a website as the final word on a particular roof. The Portal sets the principle, and building control applies it to your conservatory, your frame and your plans.
The exemption and what it covers
The Building Regulations 2010, Schedule 2, Class 7 deals with the extension of a building by adding a conservatory, porch, covered yard or covered way at ground level. It applies where the floor area of the extension does not exceed 30 m², and where a conservatory or porch is wholly or partly glazed, the glazing satisfies the requirements of Part K.
Approved Document L 2021, paragraph 0.14, gives the energy exemption separately. It applies "if all of the following apply":
- The extension is at ground level.
- The floor area of the extension does not exceed 30 m².
- The glazing complies with Part K of Schedule 1 to the Building Regulations.
- Any wall, door or window that separates the extension from the dwelling has been retained or, if removed, has been replaced with a wall, door or window.
- The heating system of the dwelling is not extended into the conservatory or porch.
All five have to be true together. A conservatory that fails any one of them is not exempt from the energy requirements, and no later condition rescues it. A roof quote that says nothing about the room's heating or its separation from the house is therefore incomplete. We note both at the survey, and a change to either is raised with building control before the work is priced.
The England wording of the last limb matters. It is about the home's heating system and whether it has been extended into the conservatory. How that reads for a particular radiator or pipe run is for building control to say, and we ask before pricing.
All five conditions must hold at once, and a roof job is the moment to check each of them.
How the exemption is lost
The exemption is a description of how the room is built and used, so it can be lost by changes that look unrelated to the roof. The table lists each condition with the change that would end it.
| Condition | What it asks | What can end it |
|---|---|---|
| Ground level | The extension is at ground level | A raised floor above ground level |
| Size | No more than 30 m² of floor | An enlargement past that area |
| Glazing | Complies with Part K | Glazing that does not meet Part K |
| Separation | A wall, door or window still divides it from the house | Removing the division without replacing it |
| Heating | The home's heating is not extended into it | Running the home's heating into the room |
The separation and heating limbs are the two that using the room all year can disturb. Knocking through to the house or adding a radiator on the house system changes the position. A new roof brings these into question, because it must comply with building regulations and building control can ask what stands between the room and the house and what heats it.
A ground-level conservatory of up to 30 m² with Part K glazing is exempt from the energy rules only while a wall, door or window still separates it from the house and the home's heating is not extended into it; a new solid roof must comply with building regulations, so we check with building control first.
Weight, and why a heavier roof is a structural question
A new conservatory roof is a structural question as well as an energy one, because the frame was designed for the roof it carries. The Planning Portal's guidance on re-roofing says Building Regulations approval is needed where a new covering "increases the weight of the roof covering by 15 per cent or more", and advises checking "with a structural engineer or surveyor before commencing with works".
Approved Document A puts it as a test on the roof as a whole: "A significant change in roof loading is when the loading upon the roof is increased by more than 15%." The two texts differ slightly, so we name whichever one we are quoting: the Portal says 15 per cent or more, and Approved Document A says more than 15%.
Both are written for roofs in general. A conservatory frame is designed for the roof it carries, and a tiled or lightweight solid roof can change the load on it, so the question is worth asking whatever the exact threshold turns out to be.
Three things are checked at survey:
- the existing roof's construction and approximate weight;
- the frame, its fixings and the dwarf walls or piers that carry the load;
- the weight of the replacement system as supplied by its maker.
We do not give a verdict from the garden. The figures go to building control and, where the structure is in doubt, to a structural engineer. Our answer on planning permission for a conservatory roof covers the separate planning question.
Who checks the work
Building control is carried out by the council's building control team or by a registered building control approver. The registration regime for private approvers started on 6 April 2024, and a council team is the other route. Either way, someone independent of the roofer looks at the work against the regulations.
The contact differs by council, and we only name the ones we can source.
- Havant addresses: your building control body, which we confirm before work starts.
- Arun addresses: Arun District Council's building control page lists replacing roof coverings on pitched and flat roofs among alteration projects that need approval, so we confirm the route with the council before a re-roof.
- Elsewhere in Hampshire, Portsmouth, Southampton and West Sussex: your building control body, which we confirm before work starts.
For a conservatory, the questions we put are the same wherever you live. Is the exemption intact? Does the new roof need to meet the energy rules? Is the frame adequate? What evidence does the inspector want to see, and at which stage? Questions about how a council treats a conservatory roof belong with the council and not with a roofer, so we put them in writing and keep the reply with the job file.
Our answers on when a conservatory is exempt from the energy rules and on running the house heating into a conservatory go further into those two conditions.
Costs, lifespans and the order of work
Third-party figures give the scale of the decision. MyJobQuote says that in 2026 the average conservatory roof replacement costs between £3,200 and £6,000, and that a tiled conservatory roof replacement typically ranges from £6,000 to £15,000. Those are published guides, not our prices.
| Roof | Published figure | Source |
|---|---|---|
| Polycarbonate | A typical lifespan of 10 years | HomeBuilding |
| Glass | Will likely last in excess of 30 years | Roofing Megastore's managing director, quoted by HomeBuilding |
| Tiled | Will typically last in excess of 50 years with little maintenance | Roofing Megastore's managing director, quoted by HomeBuilding |
None of these is a promise, and the longer ones come from a supplier's managing director.
The two ends of the cost range are not the same job. A tiled roof can bring a structural question and a building control inspection that a light replacement may not, which is part of why the published ranges sit apart. We do not set a price from the table: the survey comes first, then one written total.
The order of work is short:
- We survey the conservatory, the frame and the wall where it meets the house.
- We check the exemption conditions and the weight question, and raise any need to strengthen the frame before the quote, not after it.
- We confirm the route with your building control body.
- You receive one written total price, and nothing starts until you agree it.
The whole range is on our conservatory roofs page.