Notifiable projects

When does a roof project have to be notified to HSE?

The short answer

A roof project has to be notified to HSE if it will last longer than 30 working days and have more than 20 workers on it at the same time at some point, or if it will exceed 500 person days. The client gives the notice in writing, and it has to reach HSE before the construction phase begins. The numbers decide it, not the type of building.

Regulation 6 of CDM 2015 sets two tests for telling HSE about a project. This page sets out both and who gives the notice.

Mixed slate, clay and concrete tile rooftops of a market town

The two tests in regulation 6

CDM 2015 regulation 6 says a project is notifiable if it meets either of two tests. A project does not have to meet both, and either one is enough on its own.

The two notification tests in CDM 2015 regulation 6
TestWhat the regulation says
First testLonger than 30 working days, with more than 20 workers working at the same time at any point in the project
Second testMore than 500 person days of construction work

One person working for one day makes a person day, so the second test measures the total effort on the project, whatever the length of the programme or the size of the crew on any single day. As a rough guide to the arithmetic, 10 workers on site for 50 days is 500 person days exactly, and the test is met only by exceeding that figure. The first test needs both the length and the crowd, not just one of them.

The regulation is short and plain, and you can read it on legislation.gov.uk without any legal background, which is a good idea if you are the client on a large project: CDM 2015 regulation 6.

Who gives the notice, and when

The client must give notice in writing to the Executive, which is HSE, as soon as is practicable before the construction phase begins. For a commercial client that duty stays with the client. HSE's guidance keeps the client's duties intact for commercial clients.

For a domestic client, regulation 7(1) passes the regulation 6 duty to someone else: the contractor where there is only one, or the principal contractor if several contractors are involved, or the principal designer under a written agreement. A homeowner is not expected to file the notice themselves.

Notification is a matter of timing as well as numbers, and late notice is a missed duty, not a minor delay. The notice goes in before the construction phase starts, so the length of the job and the size of the crew have to be estimated at the survey, not discovered later. We give you our programme with the written total price, and you can check it against both tests. Our page on who the client is under CDM explains how to tell which kind of client you are.

What does not depend on notification

It is easy to assume that the extra CDM duties switch on only when a project is notifiable. They do not. The duty to name a principal designer and principal contractor turns on a second contractor being involved, or being reasonably foreseeable. That can happen on a small roof job as easily as on a large one.

The construction phase plan is also independent. Every project has one, whether or not HSE is told. For a project with a single contractor, regulation 15(5) has that contractor produce one or arrange for it, and where several are involved, regulation 12(1) gives the task to the principal contractor.

Not every commercial roof is notifiable. A flat roof on a shop, a repair to one bay of a unit or a re-cover of a small office can sit far below both numbers, so ask for the figures before assuming that notice is needed, and ask who will be giving it. A large re-roof of a unit with a big crew is where the test needs checking, because crew size and length can both be close to the limits.

Working it out on a real job

To test a project, you need three numbers: how many working days the roof work will run, the largest number of workers on it at any one time, and the total person days. The contractor's programme supplies all three, which is why we ask for the programme to be written down before the price is agreed.

Work through it in this order, with the contractor's programme in front of you:

  1. Take the programme length in working days, and compare it with 30.
  2. Find the highest number of workers on site at once, and compare it with 20.
  3. If both limbs of the first test are met, the project is notifiable.
  4. Whatever the answer, add up the person days and compare the total with 500.

If the answer is close, tell the contractor early so the arrangements can be made before the start date. A project that is only just over a limit still counts as notifiable, and one that is only just under it does not, so the programme should be realistic, not hopeful. Work in an occupied building, or on a block of flats, may run longer than expected, so our pages on roof work in an occupied building and the commercial roofing hub give the wider picture.

Related questions

Is every commercial roof project notifiable to HSE?

No. Regulation 6 sets two tests: longer than 30 working days with more than 20 workers at once, or more than 500 person days. A project that meets neither is not notifiable, although a construction phase plan is still needed and the client duties still apply.

Does a homeowner have to notify HSE about a roof job?

Regulation 7(1) passes the notification duty to the contractor, the principal contractor or the principal designer, depending on how the project is set up. The notice is not something the homeowner is expected to give, and our survey and written programme supply the figures it needs.