Part L of the Building Regulations deals with the conservation of fuel and power. For a roof it comes down to one thing: how much heat the roof lets through. That is measured as a U-value in W/m²K, and the lower the number, the less heat escapes. When a commercial roof is built or renewed, Approved Document L sets the figure the work is expected to reach.
Approved Document L comes in two volumes. Volume 1 is for dwellings and Volume 2 is for buildings other than dwellings, so shops, offices, workshops and industrial units follow Volume 2. Its figures differ from those used for houses, and picking the wrong volume is an easy mistake on a commercial job.
This guide gives the Volume 2 figures that matter for a roof, the date the next edition takes over, and the CDM 2015 and asbestos duties that sit beside Part L on the same job. Commercial roof prices are set after a survey, so none appears here.
Which edition applies, and from when
Two editions of Volume 2 matter at the moment, and the dates decide which one a job is built to.
| Edition | Takes effect | Roof tables |
|---|---|---|
| 2021, with 2023 amendments | 15 June 2022 | 4.1 and 4.2 |
| 2026 | 24 March 2027, for work not in connection with higher-risk building work | 3.1 and 3.2 |
Until 24 March 2027 the 2021 edition is the one in use. From that date the 2026 edition takes effect for the work described in the table. A job that spans the changeover is a question for your building control body, and we ask it which edition governs before the work is priced.
Building control is carried out by the council's building control team or by a registered building control approver. Volume 2 is for buildings other than dwellings, and the two volumes never swap figures. A shop, an office or a unit is held to the Volume 2 numbers below, and a house is held to the Volume 1 numbers set out in our planning guide for roof work.
On a block of flats, we confirm with your building control body which volume applies before work starts.
To tell which table applies, we need to know what the building is used for, what type of roof it has, where its insulation sits and whether the work covers all of the roof or part of it. Part L is a Building Regulations matter, so the route runs through building control, and planning is a separate question.
New and replacement roofs: the first table
Where a roof, or part of one, is new or replaced, the new-element table of the 2021 edition sets the limiting U-values. Every figure here is in W/(m²·K).
| Element | Figure |
|---|---|
| Roof, flat | 0.18 |
| Roof, pitched | 0.16 |
| All other windows, roof windows and curtain walling | 1.6 |
| Rooflights | 2.2 |
Windows, roof windows and rooflights are held to separate figures from the roof around them. A roof window on a commercial building comes under the 1.6 figure for all other windows, roof windows and curtain walling, while a rooflight takes 2.2. A new or replacement rooflight is held to the rooflight figure in the same table. In the Building Regulations a thermal element means a wall, floor or roof, and it does not include windows, doors, roof windows or roof-lights.
From 24 March 2027 the 2026 edition applies to building work that is not in connection with higher-risk building work. Its Table 3.1 gives 0.18 for a roof. We confirm the figures for the job in front of us with your building control body, because the edition and the type of building both decide which table is used.
A lower U-value normally means more insulation in the roof build-up, and that can change the thickness of the roof. A survey records the existing build-up so that the effect is known before a price is written.
Existing roofs: the threshold and the improved figure
A job that renews an existing roof is judged against Table 4.2 of the 2021 edition, not the first table. It gives two columns for each type of existing roof: the threshold, and the improved figure.
| Existing roof | Threshold | Improved |
|---|---|---|
| Pitched, insulation at ceiling level | 0.35 | 0.16 |
| Pitched, insulation at rafter level | 0.35 | 0.18 |
| Flat, or roof with integral insulation | 0.35 | 0.18 |
The row that applies depends on where the insulation sits, so the survey notes the type of roof, where its insulation is and what it is made of. Renovation should bring the roof to the improved figure for its type, and a retained roof with a U-value above the 0.35 threshold should be upgraded to it, provided that is feasible and pays back within 15 years.
Paragraph 4.8 covers the case where it cannot be done. If the improved figure is not technically or functionally feasible, or the simple payback would be longer than 15 years, the element should be upgraded to the lowest U-value that is feasible and still pays back within 15 years. "Generally, a thermal element once upgraded should not have a U-value greater than 0.7W/(m2·K)."
The 2026 edition keeps the 0.35 threshold in its Table 3.2, with an improved figure of 0.18. Until 24 March 2027, the 2021 table above is the one to use. The figure for a given job is confirmed with building control before work starts, not assumed from a table.
The row that applies follows where the insulation sits, so the survey looks there first.
When a flat roof counts as renovated
Renovation is what brings the existing-roof figures into play. Paragraph 11.2(d) lists one trigger by name: "Replacing the waterproof membrane on a flat roof."
Paragraph 11.3 then says when the whole roof element should be improved:
- "More than 50% of the surface of the individual thermal element is renovated"; or
- the work is a major renovation, which "is when more than 25% of the surface area of the external building envelope is renovated."
A new membrane on a commercial flat roof is therefore more than a waterproofing job. The insulation figure becomes part of the specification, and the survey records the roof area so that the percentages can be worked out and checked with building control. The percentages are of surface area, so each section of the roof is measured separately.
The British Standard for membrane flat roofs is BS 6229. BS 6229:2025 is shown as current and BS 6229:2018 as withdrawn. The 2025 edition covers flat roofs, or curved roofs with a pitch not greater than 10 degrees, that use continuously supported flexible waterproof coverings, which means membranes and not lead. The NFRC reports that it sets a minimum finished fall of 1:80 for general roof areas and internal gutters, and IKO says the code of practice advises a design fall of 1:40. Lead sheet roofs lie outside BS 6229, and their details are specified separately.
CDM and asbestos on the same job
Part L is only one part of the paperwork on a commercial roof. HSE's guidance on commercial clients says "A commercial client is any individual or organisation that carries out a construction project as part of a business." The duties follow from that.
- Regulation 4(1): "A client must make suitable arrangements for managing a project, including the allocation of sufficient time and other resources."
- Regulation 5(1): "Where there is more than one contractor, or if it is reasonably foreseeable that more than one contractor will be working on a project at any time, the client must appoint in writing" a principal designer and a principal contractor. The count of contractors, not notification, triggers these extra appointments. Our answer on who is the client under CDM goes through them.
- Regulation 6: a project is notifiable if it will last longer than 30 working days with more than 20 workers at once, or exceed 500 person days. Our answer on when a roof project is notifiable sets that out.
- Construction phase plan: with one contractor, the contractor must draw one up or make arrangements for one to be drawn up; with more than one, the principal contractor must draw it up. Every project has one.
Asbestos belongs on the same list. On non-domestic premises the Control of Asbestos Regulations 2012 place a duty to manage asbestos on whoever holds the maintenance or repair obligation or controls the premises, which our guide to the duty to manage asbestos explains.
HSE's sheet A14 says "AC roofs are always fragile". Careful removal of asbestos cement sheets is non-licensed work. Material that has been broken up is notifiable non-licensed work. It goes in a lockable skip, never an open one, and waste from a commercial job moves on a consignment note.
Bats, nests, fragile roofs and the written price
Several checks come before any roof is opened up. GOV.UK says all bat species and their roosts are fully protected by law, and its list of activities includes repairing or replacing a roof. Damaging or destroying a bat roost is an offence whatever the intent. A bird's nest that is in use or being built is protected too: the offence is committed by a person who intentionally takes, damages or destroys it. Both are part of the survey.
On access, HSE says all roofs should be treated as fragile until a competent person has confirmed they are not, and fragile rooflights are a particular hazard. Nobody should step onto an unfamiliar sheet roof to find out.
Commercial roofing is priced after a survey. The cost turns on the size and type of the roof, how it is reached, whether asbestos cement is present and which Part L figures the job must meet. The quote is one written total price, and nothing starts before you agree it.
What happens before a price is written:
- We survey the roof: its type, its area, its build-up and its fall.
- We check for asbestos cement and for fragile sheets or rooflights.
- We confirm the Part L route, and which edition governs, with your building control body.
- We look at who the client is under CDM and how many contractors the job involves.
- You receive one written total price.
The full range of this work is on our commercial roofing page.