023 9396 0313 Get a written quote

Party wall notices

Do you need a party wall agreement for roof work?

The short answer

Yes, when the roof work uses a right the Party Wall etc. Act 1996 lists, such as cutting away a chimney breast or cutting into a neighbour's wall to insert a flashing. The notice has to come from the owner planning the work, and for party wall work it goes out at least 2 months ahead. Ask for the question to be settled at the survey.

Roof work does not always touch a neighbour's wall, but some jobs do. When a party wall notice is needed, who serves it and how long it takes.

Tall brick chimney stacks with clay pots rising from the slate roofs of a Victorian terrace

When roof work needs a notice

The Act gives a building owner rights over a party wall, and a notice has to be served before those rights are used. Two of the listed rights come up on roofs. Section 2(2)(g) is the right "to cut away from a party wall, party fence wall, external wall or boundary wall any footing or any projecting chimney breast, jamb or flue". Section 2(2)(j) is the right "to cut into the wall of an adjoining owner's building in order to insert a flashing or other weather-proofing of a wall erected against that wall".

So removing a chimney breast on a shared wall, or cutting a flashing into a neighbour's wall, are the kinds of work that bring the Act into play. Whether your job does either is a matter of what is done to the wall, so ask your roofer to say what the survey shows rather than assuming.

A party wall surveyor, not building control, is the person to ask about the Act itself.

The legal question of notice sits with the owner, and it is worth raising early so that it does not hold up the start date once scaffold and materials are booked. If the answer is that no notice is needed, ask the roofer to say why, in writing.

Who serves it and when

The building owner, meaning the owner who intends the work, serves the party wall notice on the adjoining owner. How long before the work starts depends on the type of work:

  • For party structure work, for instance cutting away a chimney breast, the notice must be served at least 2 months before the date the work will begin (section 3(2)(a)).
  • For a new wall on the line of junction, the owner serves it at least 1 month before the work starts (section 1(2)).
  • For excavation near a neighbouring building, notice is due at least 1 month before the digging begins (section 6(5)).

A neighbour can agree to an earlier start for work to a party wall, by consent in writing: section 3(3)(a) lets the owner use the section 2 rights with the written consent of the adjoining owners and occupiers.

Build the notice period into the date you plan to start, because scaffold slots and materials are booked around it, and tell the roofer which date the notice was served. A notice served late can push the whole job back, so diarise the date it is due.

If the neighbour does not reply

The neighbour has 14 days from the day the notice is served to respond. Under section 5, an owner who "does not serve a notice indicating his consent to it within the period of fourteen days" is deemed to have dissented, and a dispute is deemed to have arisen. GOV.UK puts it simply: "You cannot assume that no response means they agree to the works."

When a dispute arises, section 10 provides for the owners to appoint one agreed surveyor, or a surveyor each. GOV.UK says: "You must appoint a surveyor if you and your neighbour cannot agree." A surveyor is therefore needed only when the neighbour dissents or has not replied within the 14 days.

The GOV.UK guide to party walls sets out the steps, and section 3 of the Act sets the 2-month rule. Build the 14 days into your planning, along with the notice period itself, and keep a dated copy of every notice and reply. If you are the neighbour receiving a notice, you can consent in writing, or you can dissent and the surveyors take over.

Chimneys, flashings and approval

Chimney work and leadwork at a shared wall are two places where roof jobs meet the Act, so each has its own answer: party walls and a chimney breast and party walls and lead flashing.

Removing a chimney breast also needs Building Regulations approval, because the Planning Portal says that approval "will always apply when removing chimney breasts as they are part of the building's structure". That is a separate step from a party wall notice, with a separate body: building control for the first, the neighbour and any surveyors for the second.

Where a roof meets a neighbouring wall is one of the places to look at the survey. Whether the Act applies is a question about what is done to the wall, so where it is in doubt, ask a party wall surveyor.

For the planning side of a roof job, the guide to planning permission for roof work is the place to read next, and the checklist for a written quote shows what to have in hand. Our other roofing answers sit on the homepage.

Related questions

Can my neighbour stop my roof work with a party wall notice?

A neighbour who dissents, or who has not replied within 14 days, creates a dispute, and surveyors are then appointed to settle it. Serving the notice correctly and early is the owner's job, so ask the survey to flag early whether a notice looks needed.

Does a party wall notice replace Building Regulations approval?

No, they are separate. A party wall notice goes to the neighbour, while building control deals with Building Regulations approval, which the Planning Portal says "will always apply when removing chimney breasts". Ask the roofer which of the two your job needs, and whether it needs both.